Everyone saw 7,000 cars. I saw 25 minutes.
Tesla celebrated a record week. An experienced plant director reads it differently: per shift, not per week, and in minutes, not percent. Three steps turn the 7,500 target into one number a team leader can act on.
1
The weekday clock is full
RunningSpecial shifts only
24/5= 15 shifts a weekR61
1,400cars a production dayR61
Every weekday hour is already used. The only hours left are weekend shifts: mandatory, at a 35% premium, agreed with the works councilR66.
2
So read the record per shift
7,000 cars ÷ 15 shifts = 467 a shift. The line could build 600C5. Per shift, the record barely moved.
No new hall. No weekend shifts. The minutes are inside shifts that already run, on a line that is already built.
A hidden factory of about 100,000 cars a yearC64: half of everything built in 2025R13, in a building, a line and a team that are already paid for.
The bottleneck has moved before. In June, 5,000 a week was “the maximum we can squeeze out of supply chain”R65. Parts now flow and the weekday clock is full, so the limit is inside the shift.
What I would put on every shift board
- 1Waiting for partslogged per stop
- 2Machine stopslogged per stop
- 3Quality holdslogged per stop
- 4New staff learninglogged per stop
- 5Model changeoverslogged per stop
Tesla doesn't publish the split, so the board fills it in from the first shift.
Three rules that come with it
- One number, for everyone. Minutes lost against a 75-minute budget, split by cause, on every shift board.
- Reviewed at every handover. The biggest cause gets an owner before the next shift starts.
- A record counts only if the minutes fall. Cars from added weekend hours are welcome, but they don't count as progress.
This is the first 30 days of the plan below: measure where the minutes go, then win them back, cause by cause.
From evidence to decision
Each step rests on the one before it. If the evidence changes, the decision changes.
- 1Evidence
467 cars a shift
The line is set to one car every 45 secondsR2, so a 7.5-hour shift could build 600C5. It built about 450 in SeptemberR1 and 467 in the record weekC62.
means - 2Diagnosis
A quarter of each shift is lost
75% is the car-industry average, far from world-class 88–90%B22. The loss is stops and waiting, not machine speed or floor spaceR16.
so - 3Decision
Stability first, then capacity
Tesla now runs the 15-shift weekR61. What is left is 83%C9: 25 minutes a shiftC63. Then secure cells, people and the permit before they bind.
proven by - 4Proof
7,500 for eight weeks in a row
That is gate G1T56. Then 7,650 a week by end-2027 at 85%C53, with no extra shifts.
How the plant works, and where it loses cars
Three streams have to arrive at the same station at the same moment. If one is late, the whole line waits.
The plant has the space. It loses the time.
Demand is there: Model Y was Europe's best-selling car in SeptemberR17. Yet the plant has never run full. The gap is time lost inside each shift.
Share of capacity used
100% = 7,500 cars a week, about 375,000 a year. The best week shows the line can do it once. The job is to do it every week.
Gate G1: weeks in a row at 7,500T56
0 of 8 so far. The best week, 7,000R10, was still 500 short of the rate.
Every 100 minutes the line could run
- Building carsC675
- Lost
Split not public25
Five causes, each already seen at Grünheide
- 1
Waiting for parts
The whole plant stopped for two weeks in 2024 for missing partsR18.
- 2
- 3
Quality holds
The annual report flags quality risk in new processesR19.
- 4
New staff learning
About 2,000 people hired for this year's rampR20.
- 5
Model changeovers
The switch to the new Model Y ran from January to February 2025R21.
Tesla does not publish how the 25 minutes split. My first 30 days: a reason code on every stop, then rank the causes by cars lost.
Engineer's notes: the throughput math
A 7.5-hour working shiftB4 is 27,000 seconds. At one car every 45 secondsR2, that is 600 carsC5. Reported output is about 450 a shiftR1, so line efficiency is 450 ÷ 600 = 75%C6.
Shifts: weekly output was under 6,500R11. 14 × 450 = 6,300, so about 14 regular shiftsC12. Two extra shifts were reported to give 7,100–7,300R23, which matches 16 × 450 = 7,200.
The plan: 7,500 a weekR7 over a normal three-shift, five-day weekR3 is 15 shifts of 500C8, which needs 500 ÷ 600 = 83%C9.
Four ways to reach 7,500 a week. Only one works.
Extra shifts alone fall short. Pushing efficiency alone asks for world-class performance on an unsettled line.
Weekly cars by route. Dots are shifts a week; orange dots are extra weekend shifts.
Where each route sits against the car industry
Share of each shift spent building good cars, the way OEE is measured. My route asks for clearly better than average, not world-class.
Fix one bottleneck and the next one appears
The limit on output moves every year or so. A good plant director fixes today's and prepares for tomorrow's.
Workstreams 1 to 3 fix today's bottleneck. Workstreams 4 to 6 stop the next ones from stalling the ramp.
Try it: which limit binds?
The plant builds the lower of two numbers: what the line can make, and what the battery cells can feed. Pick a scenario or move the levers.
Line = shifts × 600 × efficiencyC5. Cells = GWh ÷ battery size ÷ 50 weeksC29. Dashed line is the 7,500 target. Scenario presets are my assumptions.
The plan: one goal, six pillars, one operating system
Each pillar has one owner and one number to hit by end-2027.
Capital
3 gatesno spending before the evidence
Supply resilience
0critical parts with a single source
W1 Line stability: fewer stops, not faster machines
Same line, same speed. The gain comes from taking the red out of the shift.
One shift, before and after
The same random stops run in both lanes. In my plan each is fixed 40% faster, and the buffer absorbs short upstream stops.
Protect the bottleneck
The buffer is sized from measured stops. Example: riding out a 20-minute paint stop takes 27 painted bodies in stockT57. Stop positions in the timelines are illustrative; the share of red is not.
Measure every stop
A reason code at every station, ranked weekly by cars lost.
Give the bottleneck its own crew
Maintenance and quality on standby, so it never waits.
Stop and fix at the source
Help arrives within one 45-second cycle. If the fix takes longer, the line stops at a fixed pointB38.
Don't speed up yet
Keep one car every 45 seconds until 85% holds for four weeksT54.
Engineer's notes: why not cut the cycle to 40 seconds?
At 40 seconds the line could in theory build 27,000 ÷ 40 = 675 cars a shift. But a faster cycle on an unstable line multiplies stops: if efficiency fell to 65%, output would drop to 439 a shift, below today's 450.
| Measure | Today | Mid-2027 | End-2027 |
|---|---|---|---|
| Cars a shift | 450 | 500 | 510 |
| Line efficiency | 75% | 83% | 85% |
| Regular shifts a week | 14 | 15 | 15 |
| Cars a week | 6,300 | 7,500 | 7,650 |
W2 Cells and packs: the next bottleneck
Tesla says battery availability already limits its car volumeR33. Grünheide makes none of its own cells yetR26.
Where Grünheide's cells come from
Also reported in May 2026: one long-range variant now uses Tesla-made 4680 cells from the USR27.
Engineer's notes: cell demand
Need = cars a week × 50 weeks × battery size. Model Y batteries range from about 60 to 79 kWhR28; I use the middle, 70 kWh. At 7,500 a week: 7,500 × 50 × 70 kWh ≈ 26 GWh a year (22.5 to 29.6 GWh across the range)C29. 2026 uses 6,300 a week: 22 GWh.
Own cells: 18 GWh at mostR26. Even mature plants still scrap about 10%B30, so 18 × 0.9 ≈ 16 GWh of good cells, 61% of needT31. Gate design for a cell ramp is covered in my 4680 battery ramp-up case study.
W3 People: the ramp runs on people who stay
Output has to grow much faster than headcount. That only works with better onboarding and fair rules.
Output grows faster than the team
4,700 a week in Q1 2026 to 7,500; headcount at end-2025 plus the announced car hiresC39.
New hire to certified in ten weeksT37
Toyota's benchmark: about four weeks of training, then six to eight weeks on the floorB36.
How to work with the works council
IG Metall has asked a court to void the March 2026 works council electionR40. In Sweden, a strike against Tesla ran for almost three yearsR41. Sick leave fell from 15% or more to about 5%R42; protecting that gain matters.
W4 License to operate: win the permit before filing it
The site lies partly in a water protection area, and the 2023 expansion plan drew over 1,000 objectionsR44. The next hall is 2.4 times the size of the firstR43.
Who has to say yes, and what I'd offer them
Wants safe drinking water. Offer: recycling first, monthly water data.
Wants a complete filing. Offer: pre-filing reviews, phased applications.
Want less traffic and noise. Offer: a freight rail station on siteR43, a community forum.
Want transparency. Offer: water and incident data published every month.
Wants workload and job security. Offer: the framework agreement.
Wants speed. Offer: a gated plan with dates it can trust.
Decides the permit
Permit path for the 536,000 m² second hall
The law sets the clock: a decision is due seven months after a complete filing, and the agency can extend once by threeR45. A complete first filing is therefore my W4 target. The hearing is the riskiest step.
W5 Capital and W6 supply: spend on evidence, insure the weak links
In 2025 the plant earned €77.1m on €7.12bn of sales, about 1%R13. At that margin, volume is the biggest cost lever and mistakes are expensive.
Fixed cost per car
Filling the plant cuts about €2,100 a car: 5.5 times today's profit per carC47.
Fixed cost = staff costs (€745.8m) plus depreciation (€330.8m) from the 2025 annual reportR46.
Money is released only at a green light
B. Second cell line
First line at 90% good cells for four weeksT55.
C. Second product
A committed vehicle for the new hall; observers already expect oneR52.
Lights show where each gate stands today: A red (not yet at rate), B amber (cell plant not running), C green to start planning.
Supply risk map
Each risk is tagged with dated evidence; where it sits on the map is my judgement. China's pause on rare-earth export controls ends on 10 November 2026R48.
How the plant is run, every hour to every quarter
Small problems are fixed at the line within the hour. Only what can't be fixed moves up.
Meeting rhythm
How issues escalate through these levels is designed in my NPI-OS escalation framework.
The numbers on the director's wall
Line
500cars a shift
83%of shift building
Risingright first time
Supply
13 wkof cells secured
2sources per critical part
People
10 wkhire to certified
≤5%sick leave
Site
On timepermit steps
Fallingwater per car
Cost
Fallingcost per car
Gatedcapex released
Each number traces back to the plan: 500 and 83%C9, 13 weeksT35, 10 weeksT37, sick leave at today's levelR42.
36-month roadmap with four decision gates
A gate is a decision, not a date. If the evidence isn't there, the next step waits.
Swipe sideways to see all 36 months.
G1 Rate7,500 a week for eight weeks in a rowT56
G2 YieldOwn cells at 90% good for four weeksT55
G3 PermitSecond hall, phase 1 approvedR45
G4 ProductSecond product committedR52
Dates are my plan, anchored on reported milestones: hiringR20, cell start in 2027R26, filing in December 2026R43. Dark bars are active work, blue bars are battery and site work, grey bars run continuously.
What would make me change course
Warning signals agreed in advance, so the response is fast and calm.
Line still below 80% after 100 days
Stop hiring for extra shifts; bring in a line-balancing team.
Order backlog falls below six weeks of outputR33
Hold the 15th shift, protect margin, slow hiring.
Own cells below 85% good six months after startT55
Extend supplier contracts; delay the second cell line.
Court voids the works council electionR40
Support a neutral rerun; keep agreement talks going.
More objections, or tighter water rulesR44
Phase the expansion; invest in water recycling first.
China reinstates rare-earth controls after 10 NovemberR48
Draw on safety stock; switch to the second supplier.
Evidence register: every number, and where it comes from
66 entries from 32 dated sources. Filter by type, or tap any tag on the page to land on its row.
| Tag | What the page says | Evidence or formula | Source |
|---|---|---|---|
| R1 | About 450 cars a shift (September 2026) | Plant figures quoted by the press: “ungefähr 450 Fahrzeuge pro Schicht”. | S2 |
| R2 | One car every 45 seconds at key stations | Cycle cut from about 80 s to 45 s, described as largely in place. | S2 |
| R3 | Production runs three shifts | Annual report 2025: “3-Schichtsystem im Produktionsbereich”. | S1 |
| B4 | 7.5 working hours in a shift | German law requires at least a 30-minute break for 6 to 9 hours of work, so an 8-hour shift holds at most 7.5 working hours. | S26 |
| C5 | 600 cars a shift at full speed | 7.5 h × 3,600 s = 27,000 s; 27,000 ÷ 45 s = 600. | From R2B4 |
| C6 | Line efficiency 75% | 450 ÷ 600 = 75%. The other 25% of the shift is lost time. | From R1C5 |
| R7 | Target 7,500 cars a week, about 375,000 a year | Tesla's target from mid-October 2026; the annual report's capacity figure extrapolates to up to 375,000. | S2, S3 |
| C8 | Shift plan 500 cars | 7,500 ÷ 15 shifts (3 shifts × 5 days) = 500. | From R3R7 |
| C9 | 83% efficiency needed | 500 ÷ 600 = 83%. | From C5C8 |
| R10 | 7,000 Model Y built in one week | Announced by Tesla Manufacturing on X on 23 Oct 2026; Tesla gave no shift details. | S4, S5 |
| R11 | Under 6,500 cars a week before the special shifts | “weniger als 6.500 Autos” a week, per plant figures. | S2 |
| C12 | About 14 regular shifts, 6,300 cars a week | 14 × 450 = 6,300, which fits “under 6,500”. | From R1R11 |
| R13 | 2025: 202,000 cars, 54% of capacity, €7.12bn sales, €77.1m profit | Annual report 2025. Profit is 1.1% of sales. | S1 |
| R14 | Q1 2026: more than 61,000 cars | Reported production for the quarter. | S4 |
| R15 | 11,083 people at end-2025 | Including temporary staff. Average for the year: 9,976. | S1 |
| R16 | Installed capacity over 375,000 cars a year | Tesla's Q3 2026 shareholder deck, as reported. | S5, S3 |
| R17 | Model Y: Europe's best-selling car in September 2026 | 40,971 registrations, preliminary Dataforce data. | S6 |
| R18 | Parts: the plant stopped for two weeks in 2024 | Production halted 29 Jan to 11 Feb 2024 for missing parts after Red Sea attacks. The 2025 report rates supply risk medium-high. | S7, S1 |
| R19 | Machines and quality: new processes may miss target | 2025 report: new processes and technologies may not reach planned speed or quality at first (medium-high risk). | S1 |
| R20 | About 2,000 hires for the car ramp, 1,500+ for cells | Up to 3,500 new jobs announced in total for 2026. | S2 |
| R21 | Changeover to the new Model Y, early 2025 | Lines converted from end-January; only the new model built from 16 Feb 2025. | S8 |
| B22 | Auto assembly: average 70–75%, world-class 88–90% | OEE benchmarks. Across industries, world-class is 85% (90% × 95% × 99.9%), from Nakajima's work. | S9 |
| R23 | Two extra shifts give 7,100–7,300 a week | Projection for a week with two additional shifts. | S2 |
| C24 | Efficiency-only route needs 89% | 7,500 ÷ 14 shifts = 536 a shift; 536 ÷ 600 = 89%. | From C5R7 |
| C25 | Capacity used: 65% in Q1, 84% in September, 93% in the best week | 61,000 × 4 ÷ 375,000; 6,300 ÷ 7,500; 7,000 ÷ 7,500. | From R7R10C12R14 |
| R26 | Own cell plant: up to 18 GWh a year of 4680 cells from 2027 | Raised from 8 GWh in May 2026; 1,500+ jobs; $250m added. No cells are made on site yet. | S10, S3 |
| R27 | Cells today come from CATL (LFP) and LG Energy Solution (NCM) | Also reported in May 2026: one long-range variant now uses Tesla-made 4680 cells from the US. | S10, S11 |
| R28 | Model Y batteries: about 60 to 79 kWh | 60 kWh (RWD, LFP) to 79 kWh (AWD and Performance), usable capacity. | S12 |
| C29 | Cells needed: about 26 GWh a year | 7,500 × 50 weeks × 70 kWh = 26.25 GWh. Range at 60–79 kWh: 22.5–29.6 GWh. 70 kWh is the middle of the range. | From R7R28 |
| B30 | New cell plants scrap 15–30% in early years | About 10% even after five years. In the very first pilot phase, scrap can reach 80–90%. | S13, S14 |
| T31 | Own-cell scenario: 4, 11 and 16 GWh of good cells in 2027–2029 | 16 = 18 GWh × 90% good, the mature level. Shares of need: 15%, 42%, 61%. | From R26C29B30 |
| R32 | Local cells are not cheaper | Robert Meyer, Tesla's cell factory lead: “Rein kostentechnisch lohnt sich der Schritt wenig.” A strategic decision. | S15 |
| R33 | Battery supply already limits Tesla's car volume | Q3 2026 letter: battery availability “continued to be the limiting factor in increasing auto volumes”; largest order backlog in four years. | S16 |
| B34 | Asia to North Europe by sea: 42–48 days | Via the Cape of Good Hope, with the Red Sea and Hormuz routes degraded in 2026. | S17 |
| T35 | 13 weeks of cell supply secured | About two sea voyages (2 × 6.5 weeks): one in transit, one on site. | From B34 |
| B36 | Toyota: about 4 weeks of training, then 6–8 weeks on the floor | Toyota Indiana: new hires spend about four weeks learning the Toyota way and practising at training stations, then six to eight weeks on the floor. | S18 |
| T37 | New hire to certified in 10 weeks | Four weeks off the line, then on the line with a mentor, in line with the Toyota benchmark. | From B36 |
| B38 | Help within one cycle, or the line stops at a fixed position | Andon fixed-position stop: the line halts at the end of the station if the problem isn't solved within the cycle. | S19 |
| C39 | Output +60%, people +18%, output per person +35% | 61,000 ÷ 13 = 4,700 a week, to 7,500 = +60%. 11,083 + 2,000 = 13,083 = +18%. 1.60 ÷ 1.18 = 1.35. | From R14R15R20 |
| R40 | IG Metall asked a court to void the March 2026 works council election | Filed 25 Mar 2026 under § 19 of the Works Constitution Act. | S20 |
| R41 | Sweden: a strike against Tesla ran for almost three years | October 2023 to 19 August 2026; it ended without an agreement. | S21 |
| R42 | Sick leave fell from 15% or more to about 5% | 15%+ in 2024 (plant manager); about 5% in April 2026 (Tesla). | S22 |
| R43 | Second hall: about 536,000 m², filing planned for December 2026 | The existing hall is about 219,000 m². Construction from 2027 at the earliest; a freight rail station is part of a later permit. | S23 |
| R44 | Partly in a water protection area; over 1,000 objections | The 2023 site-expansion plan drew over 1,000 objections about forest, water and foundations. | S24 |
| R45 | Permit law sets the pace | 1 month of public display; objections up to 2 weeks after (1 month for industrial-emissions plants); decision within 7 months of a complete filing, extendable once by 3. | S25 |
| R46 | 2025 staff costs €745.8m, depreciation €330.8m | Annual report 2025: notes and asset schedule. | S1 |
| C47 | Fixed cost per car: €5,330 now, €3,230 at full rate; profit €382 a car | (745.8 + 330.8) ÷ 202,000 = €5,330. Staff scaled to 13,083 people = €880m; (880 + 331) ÷ 375,000 = €3,230. 77.1m ÷ 202,000 = €382. | From R13R15R20R46 |
| R48 | China's rare-earth export pause ends 10 Nov 2026 | The wider US–China truce runs to 10 Jan 2027; no renewal of the pause was confirmed by 5 Nov. | S27 |
| R49 | Simple chips: the Nexperia halt of October 2025 | China blocked Nexperia exports; the German auto lobby warned of possible production stops. | S28 |
| R50 | Aluminium: Gulf supply disrupted | The Gulf supplies about 15% of Europe's aluminium; one major smelter may need up to 12 months to restore output. | S29 |
| R51 | Memory chips: shortage reaching car makers | Industry report on the 2026 memory crisis in automotive. | S30 |
| R52 | Up to 1 million cars long term; a second vehicle expected | Site ambition reported in October 2026; observers expect another vehicle besides the Model Y. | S23 |
| C53 | 7,650 cars a week by end-2027 | 15 shifts × 510 (85% of 600) = 7,650. | From C5T54 |
| T54 | Line efficiency 85% by end-2027 | Above the auto average (70–75%), still below auto world-class (88–90%). | From B22 |
| T55 | Own cells: 85% good before adding shifts, 90% before a second line | 85% is the top of the early-years range; 90% is the mature level. | From B30 |
| T56 | Gate G1: 7,500 a week for eight weeks in a row | One record week is not a rate. Eight weeks covers two monthly reviews. | From R10 |
| T57 | Buffer before the bottleneck sized from measured stops | Example: a 20-minute paint stop needs 27 bodies in stock (20 min × 80 cars an hour ÷ 60). | From R2 |
| C58 | At least 24.5 GWh a year of bought-in cells | The 7,000-car week at that pace: 7,000 × 50 × 70 kWh = 24.5 GWh a year. | From R10C29 |
| R59 | Exports to more than 30 markets | Giga Berlin supplies more than 30 markets, as reported with the 2025 annual results. | S3 |
| R60 | Shift groups Blue, Red and Silver | The plant's three shift groups, named in reporting on the September 2026 special shifts. | S2 |
| R61 | The plant runs 24/5: 15 shifts a week | Plant manager André Thierig, replying on X after the 7,000-car week: the factory currently runs 24/5, about 1,400 cars per production day. | S31 |
| C62 | About 467 cars a shift in the record week: 78% efficiency | 7,000 ÷ 15 shifts = 467; 467 ÷ 600 = 78%. If that week also had weekend shifts, the rate per shift was lower. | From R10R61C5 |
| C63 | Minutes lost per shift: about 112 in September, 100 in the record week, 75 allowed at target | Each missing car is one 45-second cycle. (600 − 450) × 45 s = 112 min; (600 − 467) × 45 s = 100 min; (600 − 500) × 45 s = 75 min. The gap to target: 25 minutes a shift. | From R1R2C5C8C62 |
| C64 | Hidden factory: about 100,000 cars a year | 133 lost cars a shift × 15 shifts × 50 weeks = 99,750: about half of the 202,000 cars built in 2025. | From R13R61C62 |
| R65 | June 2026: 5,000 a week was the supply-chain limit | Thierig: the plant is “running right now just about 5,000 cars a week. That's right now the maximum we can squeeze out of supply chain.” | S32 |
| R66 | Weekend shifts: mandatory, 35% premium, agreed with the works council | Three mandatory special shifts in September 2026. Tesla pays a 35% premium for extra work; the special shifts were agreed with the works council. | S2 |
Sources (32)
- Tesla Manufacturing Brandenburg SE, Jahresabschluss 2025 (annual financial statements), filed in the German Bundestag lobby register, 2026. lobbyregister.bundestag.de
- Industriemagazin (T. Arnold), Tesla Grünheide: Sonderschichten sollen Europas wichtigste Gigafactory auf Kurs bringen, 7 Sep 2026. industriemagazin.at
- electrive.net (J. Apitzsch-Krause), Tesla steigert Gewinn in Grünheide und will Produktion hochfahren, 20 Jul 2026. electrive.net
- Tesla North (S. Lee-Jones), Giga Berlin hits 7,000 Model Y in one week, 23 Oct 2026. teslanorth.com
- Drive Tesla Canada (D. John), Tesla produces 7,000 Model Ys in one week at Giga Berlin, 23 Oct 2026. driveteslacanada.ca
- Drive Tesla Canada, Model Y is Europe's best-selling car in September (Dataforce data), 20 Oct 2026. driveteslacanada.ca
- autohaus.de (dpa), Tesla: Produktion in Grünheide für zwei Wochen ausgesetzt, 29 Jan 2024. autohaus.de
- ecomento, Produktion in Grünheide jetzt auf neues Model Y umgestellt, 18 Feb 2025. ecomento.de
- TEEPTRAK (R. Singh), World-class OEE: what is it and how close are you?, 20 Apr 2026. teeptrak.com
- electrive.com (C. Werwitzke), Tesla expands Grünheide battery cell plans to 18 GWh annually, 13 May 2026. electrive.com
- InsideEVs Germany, Tesla Model Y (2026): Weniger Reichweite durch neue 4680-Zellen?, 8 May 2026. insideevs.de
- InsideEVs Germany, Tesla Model Y (2026): Alle Daten, Preise und Reichweiten, updated 18 May 2026. insideevs.de
- Fraunhofer FFB and RWTH Aachen PEM, white paper: Mastering Ramp-up of Battery Production, 17 Oct 2024. ffb.fraunhofer.de
- Autoweek (J. Motavalli), Battery plant scrap rates can hit 90% at ramp-up, 5 Feb 2024. autos.yahoo.com
- ecomento, Tesla-Manager: Warum der Konzern Akkus in Grünheide fertigen will, 6 Oct 2026. ecomento.de
- Electrek (F. Lambert), Tesla's Q3 2026 shareholder letter: battery supply limiting sales, 21 Oct 2026. electrek.co
- Cargolinked, Red Sea and Cape routing in 2026: network effects, 5 Aug 2026. cargolinked.com
- Toyota Newsroom, How Toyota's Kentucky and Indiana plants train team members, 10 Mar 2026. pressroom.toyota.com
- Lean Enterprise Institute, Lean Lexicon: Andon. lean.org
- IG Metall, press release: IG Metall ficht Betriebsratswahl bei Tesla an, 25 Mar 2026. igmetall.de
- Drive Tesla Canada, Tesla prevails as IF Metall ends nearly three-year strike in Sweden, 13 Aug 2026. driveteslacanada.ca
- t-online (dpa), Krankenstand in Tesla-Werk in Grünheide gesunken, 29 Apr 2026. t-online.de
- electrive.net, Teslas Expansionspläne für Grünheide werden konkret, 16 Oct 2026. electrive.net
- Berliner Zeitung (dpa), Tesla-Erweiterung in Grünheide: mehrere Einwände eingegangen, 22 Dec 2023. berliner-zeitung.de
- Federal Immission Control Act (BImSchG), § 10 approval procedure, current text. gesetze.legal
- Working Hours Act (ArbZG), § 4 rest breaks, current text. buzer.de
- The Motley Fool (C. Carlsen), China's rare-earth export pause expires Nov. 10, 5 Nov 2026. fool.com
- Bloomberg via Claims Journal, Europe auto industry braces for chip disruption within days, 21 Oct 2025. claimsjournal.com
- Petromindo, Hormuz disruption hits Gulf aluminium output, recovery may take months (IAI), 11 Apr 2026. petromindo.com
- Counterpoint Research, Memory crisis in the automotive industry: how suppliers and automakers are responding, 22 Aug 2026. counterpointresearch.com
- EVwire (S. Alvarez), Tesla Giga Berlin builds 7,000 Model Ys in a single week for the first time, nears 7,500 target, 26 Oct 2026. evwire.com
- EV / eletric-vehicles.com, Tesla's GigaBerlin maxes out supply chain as German sales surpass full 2025 (interview with Tesla Owners of Silicon Valley), 18 Jun 2026. eletric-vehicles.com
What this project shows
Diagnosis
Telling a stability problem from a capacity problem, and seeing the next bottleneck early.
Engineering math
Cycle time, efficiency, shifts, cells and staffing, calculated rather than guessed.
Evidence discipline
Every number tagged and traced to a dated source, a formula, a benchmark or a stated decision.
Leadership
Works council, permits and neighbours treated as production risks.
Capital discipline
Every euro of new capacity tied to evidence through gates.
Limits and disclaimer
Built from public sources up to 5 November 2026, without access to plant data. Where the public record stops, I say so: the split of lost time is not public and is the first thing I would measure. Scenarios and targets are marked as my call and show the reasoning behind them.
Independent case study. Not produced for, commissioned by or endorsed by Tesla, Inc., its suppliers, IG Metall or any authority. Company names describe public facts only.
Related work: EV Factory in Motion, Tesla NPI-OS, 4680 battery ramp-up.